Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing is a privileged achievement one could be graced with. But adverse to the general notion certifying with Microsoft is not that challenging if the candidates have proper preparation material to pass the Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing exam with good grades. Questions answers and clarifications which are designed in form of Pass4cram dumps make sure to cover the entire course content. Pass4cram have a brilliant MB-320 dumps pdf with the most recent and important questions and answers in PDF files. Pass4cram is sure about the exactness and legitimacy of Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing dumps and in this manner. Candidates can easily pass the Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing exam with genuine Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing dumps, and get MICROSOFT certification. These dumps are viewed as the best source to understand the Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing well by simply pursuing examples questions, and answers. If a candidate completes practice the exam with certification MB-320 dumps along with self-assessment to get the proper idea on MICROSOFT accreditation and to ace the certification exam.

 

NEW QUESTION 73
You are a functional consultant for Contoso Entertainment System USA (USMF).
You need to create a calendar for USMF that uses factory shifts of 06:00 to 14:00 from Monday to Friday.
To complete this task, sign in to Dynamics 365 portal. You must complete Task 1 before completing this task. Task 1 is the creation of the working time template.

Answer:

Explanation:
See explanation below.
Explanation
We need to configure a calendar to use the working time template we configured in the previous question.
* On the home page, select Resource lifecycle management.
* Select Calendars.
* Select New.
* In the Calendar field, classify your calendar. This is the ID of the calendar, which is used as a reference when assigning calendars, such as to an operations resource or a resource group.
* In the Name field, name your calendar.
* In the Standard work day in hours field, enter a number.
* Make sure the row is selected, then select Working times from the Action Pane.
* Select Compose working times. Generate working hours for each day in the period where you want to be able to schedule work. As time goes by, you can generate working times for additional periods.
* In the From date field, enter a date. This is the first day that this calendar must be open.
* In the To date field, enter a date. This is the last day that this calendar is open.
* In the Working time template field, enter or select a value. The working time template defines the working hours for each day of the week.
* Select OK.
* Close the page.
Reference:
https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/create-working-time-templates
https://docs.microsoft.com/en-us/dynamics365/human-resources/hr-personnel-create-working-time-calendar

 

NEW QUESTION 74
A company plans to implement Dynamics 365 for Finance and Operations.
You need to determine which manufacturing solutions to use.
Which manufacturing solution should you use? To answer, drag the appropriate setting to the correct drop targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

 

NEW QUESTION 75
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You have created the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You create separate subcontracting purchase orders to account for the service. You attempt to add the service item to the BOM. The system generates an error.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

* Create a new item model group and select stocked product option.
* Assign the item model group and select the stocked product option (here it is selected in option one so no need to select).
* Add the service item to the BOM

 

NEW QUESTION 76
A chemical manufacturing company uses Dynamics 365 for Finance and Operations. A batch of material has a quality issue and must be reworked.
You need to create the rework order the production.
Which three options must be set? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

  • A. Set the batch order as a rework batch
  • B. Pick the reworked inventory after estimation
  • C. Reserve the reworked inventory after estimation
  • D. Specify the batch number of the batch order
  • E. Set the item as a Formula production type

Answer: A,C,E

Explanation:
Section: Create, process, and manage production batch orders

 

NEW QUESTION 77
A company manufactures high-end speaker systems. You have different configurations available for customers to customize features including finishes and speaker materials. You have a product configuration model with bill of material lines and conditions for each component.
A customer can optionally add on protective covers, but only if a non-metal material is selected. If any other material is selected, the covers cannot be added. You add the following attributes:
You need to create an expression-based constraint that will only allow Corner Protection if Metal is not selected.
How should you complete the expression? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

Explanation

 

NEW QUESTION 78
You are a production manager at a company that has implemented lean manufacturing using Dynamics 365 for Finance and Operations.
You have created a new Kanban rule to replace one that is expiring.
You need to determine the impact to the existing process jobs.
How are the active Kanbans of the expired rule handled?

  • A. The active Kanban handling units are registered as empty and new Kanbans are created.
  • B. The active Kanbans are counted as Kanbans of the replaced rule.
  • C. The active Kanbans are cancelled.
  • D. The active Kanbans are set to add to the requested period and distribute for the replacement rule time fence.

Answer: D

Explanation:
Section: Create and manage production and lean orders

 

NEW QUESTION 79
You are a functional consultant for Contoso Entertainment System USA (USMF).
You need to configure the system to ensure that a production release to a warehouse only occurs when the complete list of required components for a product is physically available.
To complete this task, sign in to Dynamics 365 portal.

Answer:

Explanation:
See explanation below.
* Navigate to Production control > Setup > Production parameters.
* Configure the Reservation field to Require full reservation.
Reference:
https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/set-up-production-processes-in-a-warehouse

 

NEW QUESTION 80
A company implements Dynamic 365 for Finance and Operations. You run the latest master plan. You observe invalid results.
You need to set up tracing for the master plan.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

Explanation

 

NEW QUESTION 81
A company makes engine parts used in the automotive industry.
They are in the process of retooling an existing manufacturing plant. They are looking to use Dynamics 365 for Finance and Operations to help support the Bill of Materials (BOM) product lifecycle for engineering version control.
You must translate existing production processes into the proper elements. You need to create BOM lifecycle states to translate existing production processes into the proper elements.
What type of BOM product lifecycle state should you create? To answer, select the appropriate BOM state in the answer area.

Answer:

Explanation:

Explanation

 

NEW QUESTION 82
A customer produces light projection toys for holiday decorations throughout the year. Because holidays vary by region and time of year, the company wants to implement Lean manufacturing.
The production process creates the toys at the following work cell: stands, main assembly, electric, visuals, and packaging.
You need to implement the production process.
Which configuration options should you use? To answer, select the appropriate configuration options in the answer area.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

Explanation

 

NEW QUESTION 83
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
* Edit the existing production flow and set the expiration date to the end of the month.
* Using the existing production flow, create a production flow and version. Set the expiration date to the end of the month. Create an activity for the new process step and add it in the proper sequence.
* Create a Kanban rule that uses the last day of the month as the effective date.
* Edit the existing Kanban rule. Set the expiration date to the end of the month. Set the new Kanban rule as the replacement Kanban rule.
* Activate the new production flow.
Does the solution meet the goal?

  • A. No
  • B. Yes

Answer: B

 

NEW QUESTION 84
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
1.) Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01
2.) Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell
3.) Create a production flow process activity using the painting work cell and the service item as the picking activity
4.) Create a service term on the activity to tie the purchase agreement to the activity Does this solution meet the goal?

  • A. No
  • B. Yes

Answer: B

Explanation:
Explanation/Reference:
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity- based-subcontracting

 

NEW QUESTION 85
A company uses Dynamics 365 for Finance and Operations for Process manufacturing.
Employees spend considerable time cleaning and setting up machines in a specific area between production orders. You must group production activities to optimize cleaning and set up time.
You need to set up the system.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: More than one order of answer choices is correct. You will receive credit for any of the correct orders you select.

Answer:

Explanation:

 

NEW QUESTION 86
A company produces homeopathic lotions for pain relief and uses Dynamics 365 for Finance and Operations. You have replaced the vendor of a product's active ingredient with a new vendor. The new vendor is supplying the ingredient at a higher concentration of 25 percent.
The previous vendor concentration was 15 percent. You are consistently running out of two of the complimentary ingredients.
You need to update the formula and ingredient settings to allow for better order planning.
What should you do?

  • A. Modify the minimum and maximum value of the attribute for the active ingredient
  • B. Modify the factor value of the compensation principle
  • C. Modify the target value of the attribute for the compensating ingredients
  • D. Modify the target value of the attribute for the active ingredient

Answer: B

 

NEW QUESTION 87
You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods. The company must track variances in material compared to the original estimated amount You must only use one picking list journal for each production order. You need to post a picking list that accounts for the material required to produce 105 finished goods. What should you do?

  • A. Report as finished five additional units in the error quantity field.
  • B. Post a picking list for 100 to account for the originally estimated amount.
  • C. Post a picking list for 100 to account for the originally estimated amount. Post an additional picking list to account for the equivalent amount of material to produce 5 finished goods.
  • D. When creating the lines for a picking list, set the value of the quantity option to 105.

Answer: B

 

NEW QUESTION 88
A company produces homeopathic lotions for pain relief and uses Dynamics 365 for Finance and Operations.
Several components used in the production of the pain-relieving lotion and oils have special government-mandated reporting requirements.
You need to ensure the company can provide the appropriate reporting and tracking for these components.
Which parameters should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

 

NEW QUESTION 89
A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?

  • A. Build capability related to length and assign to the appropriate resources.
  • B. Configure the Data/Hour option on the Capacity unit field on the resource.
  • C. Create a resource for each length.
  • D. Create a resource group for each length.

Answer: A

Explanation:
Explanation/Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-resource- capabilities

 

NEW QUESTION 90
You need to set up the configuration model to price the motorcycles correctly. What should you do?

  • A. Set Order type in price model to Sales Order and Pricing method in Version to Cost based.
  • B. Set Order type in price model to Sales Quotation and Pricing method in Version to Cost based
  • C. Set Order type in price model to Sales Quotation and Pricing method in Version to Attribute based.
  • D. Set Order type in price model to Sales Order and Pricing method in Version to Attribute based

Answer: D

 